In 1995 and 1996, I built a Bastidon in Provence (South of France). The project had 21 tasks (2 tasks canceled), it was planned for a duration of 33 man-day, realized in 47 man-day, used 5 m³ of concrete, 2000 kg of ciment, 300 rubble stone, 8 m³ of sand and gravel and about 100 kg of iron. All the details are defined in the document Bastidon Lou Mistraou.

Here are some pictures of the building.

Fondations
Les fondations (T2)
Dammage
Un peu de dammage (T3)
Beton
Du beton, un peu (T4)
Murs
En bas des murs (T6)